Installation Guides

Field manuals, grouped by system.

Written at the mill for the crew that sets the parts. Each manual carries the code reference, the layout method, the fastening schedule and the troubleshooting that saves a call-back. Start with the site conditions; they are what the warranty assumes.

Manuals
9 PDFs, free
Systems
4 — treads, railing, trim, tops
Basis
AWS · IRC R311 / R312
Before delivery

Jobsite conditions every manual assumes

Solid hardwood moves with moisture. These six conditions are what keeps a tread flat, a rail straight and a countertop joint closed — and they are the conditions the UWP warranties are written against.

  1. Moisture content at delivery

    Solid hardwood leaves the Tanner Rd mill at 6–9% moisture content, the AWS interior range. Store it flat, off the slab, in the conditioned space.

  2. Building conditions

    HVAC running and holding 35–55% relative humidity, 60–80 °F, for at least 5 days before delivery. Wet trades — drywall, paint, tile — finished and dry.

  3. Acclimation

    Treads, wide boards and countertops: 5–7 days in the room, stickered. Trim and mouldings: 48–72 hours. Do not acclimate in a garage.

  4. Subfloor and framing

    Stringers and landing framing flat within 1/8″ over 10′. Riser faces plumb. Existing treads sound and dry before a retro-fit overlay goes on.

  5. Adhesive and fasteners

    Polyurethane construction adhesive plus mechanical fasteners on every tread; finish nails in trim at 16″ centers into framing. Fastener and adhesive schedules are in each manual.

  6. Finishing

    UWP supplies unfinished unless ordered pre-finished. Sand to 120–150 grit, seal all faces of treads and countertops, and apply the specified sheen before final fastening where the schedule allows.

Manuals

Stair Treads & Risers

Solid edge-glued treads, risers and landing tread — full build over new stringers or a retro-fit overlay over an existing stair.

Manuals

Railing Systems

Balusters, newels, handrail and fittings. Pick the system first — post-to-post or over-the-post — then the manual that matches.

Manuals

Mouldings & Trim

Baseboard, casing, crown, chair rail, shoe, panel mould and transitions in solid hardwood or primed finger-jointed pine.

Manuals

Wood Countertops

Wide-plank, edge-grain and end-grain butcher block. Acclimation and expansion-hole fastening are the two rules that matter.

Field support

A question the manual did not answer?

Call the mill from the site. The people who wrote the manuals mill the parts, and a five-minute call beats a return trip.